Work Overtime If You Must Minister Charges Contractors On GARID Project
Mon, 15 Apr 2024 01:00
Minister for Works and Housing, Kojo Oppong Nkrumah has tasked contractors working on the Greater Accra Resilient and Integrated Development (GARID) project to expedite construction works to mitigate the risk of flooding in the Capital during the rainy season.
The Minister’s directive came in a meeting on Friday, April 12, 2024 with project coordinators and contractors to address delays plaguing the crucial initiative.
"We've assessed how far the project is going and we've had a number of site visits to see for ourselves the kind of work that's going on. After this appraisal, it's fair for us to say that the project is not moving as quickly as we all expected," he said.
He highlighted various bottlenecks hampering the project. The initial project framework, the Minister explained, mandated a two-step review process for every task, creating unnecessary delays. Additionally, compensating project-affected residents to facilitate work in certain locations encountered setbacks.
Further, the Minister pointed out instances where contractors deviated from project specifications without seeking prior approval. Perhaps the most concerning delay stemmed from a budgetary reallocation with a significant portion of project funds, estimated at $65 million, diverted towards COVID-19-related expenditures.
Addressing the Hurdles
The Minister outlined a series of measures to tackle these obstacles. To address the compensation delays, he announced that provisions have been made to ensure swift payments to affected residents, freeing up crucial work areas.
On the financial front, Mr. Oppong Nkrumah reassured contractors that the government is actively working with Parliament to make available the exceptional funds, including the diverted $65 million.
A Race Against Time
While acknowledging the obstacles, Mr. Oppong Nkrumah emphasized the urgency of the completion of the GARID projects. He said the impending rainy season poses a serious threat to flood-prone communities hence, contractors must act swiftly to safeguard lives and infrastructure.
He reassured contractors of the Ministry’s support in providing the needed support to ensure work progresses with speed.

Ablakwa Expresses Displeasure OverLands Commissions Failure to Provide an Up to date Data on public lands
Galamsey Menace Requires A Holistic Approach Archbishop Bonaventure Kwofie
Kaya Tours Management Services Ltd Announces Godwin Dogbey As Man Of The Year 2023
Yagbonwura Angry With Me For Failing To Cause The Arrest Of Some Gonja Chiefs Abu Jinapor
Fidelity Bank Constructs Mechanized Borehole For Police Public Safety Training School
Stanbic Bank Collaborates With Georgetown University To Enhance Service Delivery